During September 2026, construction on Brisbane Stadium and the National Aquatic Centre will continue, delivering on the Games promise and community legacy.

Brisbane Stadium

A reminder, throughout September works will include:

  • continued construction of haul roads and stockpile sites
  • earthworks including the handling of existing onsite contaminated materials in accordance with relative legislation requirements and controls
  • onsite utility works including sewer, electrical, telecoms and gas feeds (no expected outages) requiring a temporary shoulder closure on Herston Road
  • construction of a temporary shared user path, location shown on the map overleaf. More information will be provided ahead of opening in the coming weeks
  • ongoing installation of environmental controls.

What to expect

  • continuation of targeted clearing and vegetation removal for construction areas
  • demolition of redundant infrastructure and services
  • installation of new site perimeter fencing (2.1-metre-high chain mesh and barbed wire)
  • large machinery and plant movements to and from site (including out-of-hours deliveries to accommodate traffic requirements).

The history of Victoria Park

Victoria Park has had a varied past, including being a dump, a military base and affordable housing quarter among many other uses over the past 150 years. Due to this, finding contaminants in the ground while works are being undertaken is to be expected. To appropriately plan for the construction of Brisbane Stadium and the National Aquatic Centre, site investigations have been completed across Victoria Park to understand existing ground conditions. Contaminated materials were confirmed to be located throughout the area. When contaminated materials are encountered, appropriate management procedures and relevant regulatory requirements will be followed to ensure the safety of our workers and the public.

National Aquatic Centre

Initial Works

The site of the National Aquatic Centre is now secure with all fencing installed. Initial works continue including building and site investigations.

What to expect

From mid-September work onsite will include:

  • decommissioning redundant infrastructure and services within Centenary Pool and park
  • site survey and in-ground service identification
  • historical and cultural heritage surveying
  • work to widen a section of footpath on Gregory Terrace (see map for location) intermittently over a 4 week period Footpath users are asked to follow traffic control and signage to safely navigate the area. Work may occur at night due to traffic permits.

Work hours – Brisbane Stadium and National Aquatic Centre

Most construction activities are planned during standard works hours between 6.30am and 6.30pm, Monday to Saturday. Out-of-hours delivery of oversized equipment will occur due to traffic requirements.

All work is subject to approvals, construction conditions and weather. GIICA is committed to minimising the impact of construction activities on the surrounding community as much as possible.