From September 2026, both Brisbane Stadium and the National Aquatic Centre will be under construction, marking a major step forward for 2032 Games venues.
Brisbane Stadium
Early works
Early Works on the Herston side of Victoria Park will continue in September with site preparation works required for future stadium construction.
What to expect
- Work on the Herston side of Victoria Park throughout September will include:
- commencement of earthworks within the stadium footprint, including the use of excavators, bulldozers, and large dump trucks
- construction of internal haul roads and stockpile locations including excavators, compactors and rollers
- continuation of clearing and vegetation removal for construction areas
- ongoing installation of environmental controls
- onsite utility works including sewer, electrical, telecoms and gas feeds (no expected outages)
- installation of semi-permanent site fencing • demolition of redundant infrastructure and services
- construction of a shared user path, adjacent to Gilchrist Avenue, for a future diversion (more information to be provided prior to opening)
- delivery of large machinery and plant to site (including out-of-hours delivery to accommodate traffic requirements)
National Aquatic Centre
Initial Works
From 1 September 2026, initial works will commence onsite for the new National Aquatic Centre and current Centenary Pool. Public access to the western section of the park will be maintained. Please note as works progress the construction footprint will continue to change.
What to expect
Work on the Spring Hill side of Victoria Park throughout September will include:
- installation of temporary fencing around the construction site, commencing late August (see map below)
- decommissioning redundant infrastructure and services within Centenary Pool and park
- site survey and in-ground service identification
- historical and cultural heritage surveying
- possible vegetation pruning within the construction site
- service investigations including borehole drilling by Energex (outside the GIICA fenced area).
Work hours – Brisbane Stadium and National Aquatic Centre
Construction activities are planned during the standard works hours of 6.30am and 6.30pm, Monday to Saturday. Out-of-hours delivery of oversized equipment will occur to accommodate traffic requirements. For any out-of-hours or night works, impacted stakeholders will be notified individually. All work is subject to approvals, construction conditions and weather. GIICA is committed to minimising the impact of construction activities on the surrounding community as much as possible.
Help shape the future of the Victoria Park Precinct
including Brisbane Stadium and the National Aquatic Centre
The Victoria Park Precinct is set to play an important role in Brisbane’s future.
A draft legacy plan has been developed to explore how the precinct could evolve over time – balancing open space, recreation, culture, events, accessibility and community needs.
What’s proposed?
The draft legacy plan outlines a long-term vision for the precinct, including: • green and public spaces • recreation and sporting facilities • cultural and community spaces • event opportunities • improved accessibility and connections • key places like Brisbane Stadium, the National Aquatic Centre and Brisbane Showgrounds.