During November 2026, work on Brisbane Stadium and the National Aquatic Centre continues, delivering on the 2032 Games promise and community legacy.
Brisbane Stadium
Early works
Work on the Herston side of Victoria Park throughout November will include:
- ongoing earthworks and construction of haulage roads requiring the use of excavators, bulldozers, and large dump trucks • transporting and placing materials at temporary and permanent stockpile locations
- construction of a shared user path, adjacent to Gilchrist Avenue, for a future diversion (more information to be provided prior to opening)
- installation of semi-permanent security fencing
- demolition of redundant infrastructure and services
- continuation of targeted vegetation clearing as required, including use of qualified personnel and fauna management measures ongoing installation of environmental controls

Bulk earthworks update
Bulk earthworks, including management of contaminated materials is progressing as planned and will continue throughout November. Where possible, materials are being reused on site as a key sustainability measure. Management of contaminated materials is being undertaken by licensed professionals in accordance with Environmental Protection Act, 1994, Environmental Protection Regulation 2019, and Work Health and Safety regulatory Requirements.
National Aquatic Centre
Initial works
Work on the Spring Hill side of Victoria Park throughout November will include:
- survey of existing structures
- geotechnical investigations, requiring borehole drilling
- utility investigations
- minor footpath construction activities at the far end of Victoria Park near Bowen Bridge Road and Gregory Terrace. Refer to map below
- investigations may occur outside the main site fenced area.
Work hours – Brisbane Stadium and National Aquatic Centre
Most activities are planned from Monday to Saturday 6.30am and 6.30pm. Additional notification will be provided ahead of out of hours works if required.
To minimise impacts on local roads, plant and material delivery may be undertaken outside of peak traffic periods.
All work is subject to relevant approvals, construction conditions and weather.
We thank you for your understanding while work is underway at Victoria Park.
Related construction notices
No results found.
.webp&w=3840&q=75)